Biomass firing CHP 35 MWth and hot water boiler plant
Kyiv, Ukraine
August 2014 - December 2014
The following scenarios for building a biomass energy source during the study were analyzed:
- Thermal power plant with a heat output of 35 MW in a wood chip (one power unit);
- Thermal power plant with a thermal capacity of 35 MW on a wood chip (two power units with a heat capacity of 15−20 MW each, successive construction and commissioning of units);
- Thermal power station with a heat output of 35 MW on straw pellets;
- Thermal power station with a heat output of 35 MW on straw pellets (two power units with a heat capacity of 15−20 MW each; successive construction and commissioning of units);
- Hot water boiler house (DHW) with a capacity of 35 MW on a woodcut;
- Hot water boiler house (DHW) with a heat output of 35 MW on a wood chip (two boilers with a heat capacity of 15−20 MW each, successive construction and commissioning of boilers);
- Hot water boiler (DHW) with a heat output of 35 MW on straw pellets;
- Hot water boiler house (DHW) with a capacity of 35 MW on straw pellets (two boilers with a heat capacity of 15−20 MW each, successive construction and commissioning of boilers).