Within one month, the Pro-Energy team completed the installation and commissioning of the AVUS 1000 Plus cogeneration unit, integrating it into the infrastructure of the existing retail facility without interrupting operations.
1 month
natural gas
The client had already invested in a combined heat and power plant, having purchased the equipment from our partner, 2G, and was looking for a reliable partner to commission it.
The key challenge was not simply to carry out the installation, but to ensure the system could be brought online quickly within the existing retail premises, where any power supply disruptions directly affect tenants, day-to-day operations, and revenue.
Further constraints were the tight deadlines and the need to work with equipment that had already been purchased, which required strict adherence to the manufacturer’s technical specifications.
Fuel: natural gas
Electrical output: 1000 kW
Thermal output: up to 1045 kW (at 100% load)
Overall efficiency: up to 89.4%
The project resulted in the implementation of a practical distributed generation model at a commercial property, enabling the client to monitor energy consumption, improve operational reliability, and reduce the impact of external factors.
This case study demonstrates Pro-Energy’s ability to rapidly integrate cogeneration solutions into existing facilities — in compliance with the manufacturer’s standards, within a short timeframe, and without disrupting the client’s operations.
Contact our managers for a free consultation and learn about the benefits, cost, and payback of the project for your business.
Thank you for your request! The manager will contact you shortly to answer all your questions.
In the meantime, check out our implemented projects.
Periodically, you will receive letters from us with all the latest news from the field of bioenergy.
So that the letters do not end up in spam, please add info@pro-energy.com.ua to the list of contacts in the mail.
We will be in touch!