The construction of a biogas plant takes an average of 18–24 months — this is the time required to progress from the initial consultation to the full-scale commissioning of the facility under a standard scenario. It is a complex engineering process comprising seven consecutive stages — from the feasibility study to commissioning.
The longest stage is obtaining the necessary permits (6–9 months). The most expensive stage is the purchase of equipment and construction and installation work (together accounting for up to 85% of the budget).
At the same time, the actual construction timescales for biogas plants and the final budget rarely stay within the initial parameters. The main reason is mistakes made at the start of the project. An inaccurate assessment of raw materials, a poorly considered site choice, or the lack of a contingency budget can extend the project timeline by months and add 10–20% to the cost.
This article is a practical guide for farm owners, agricultural businesses, and investors interested in building a biogas plant. We have compiled real-world construction timelines, common pitfalls, and a breakdown of costs — without any vague generalisations.
Building a biogas plant involves seven sequential steps, from the initial idea to reaching design capacity. Following this process minimises the risk of delays and cost overruns. Below is an overview of the entire project, including timelines.
| Stage | Title | Term | Responsible |
| Stage 1 | Preliminary analysis and feasibility study | 1–2 months | EPC contractor, consultant |
| Stage 2 | Design (P/RP stage) | 2–4 months | Design institute, contractor (preferably an official partner of the supplier) |
| Stage 3 | Permit documentation | 6–9 months | Client + contractor |
| Stage 4 | Procurement of equipment | 7–12 months | Supplier |
| Step 5 | Construction and installation works | 6–10 months | Main contractor |
| Stage 6 | Commissioning work | 1–2 months | Supplier / service engineers |
| Stage 7 | Putting into operation and reaching full capacity | 1–2 months | EPC contractor + regulatory authorities |
Total project duration: 18–24 months. Carrying out certain stages in parallel (for example, procuring and manufacturing equipment whilst permits are being obtained) enables a reduction in duration to 14–18 months.
For projects involving the construction of a biomethane plant, the timeframe may be longer due to additional stages of integration into the gas network and the lengthy manufacturing process for ancillary equipment. In such cases, the construction timeframe for biomethane plants is often extended by 2–4 months.

A feasibility study is the cornerstone of any project. Without it, it is impossible to accurately determine the plant’s capacity, select the appropriate technology, or calculate the payback period. Skipping this step is like building in the dark.
At this stage, biogas production is still being assessed on paper: how much raw material is available, how it should be used, and what the project’s actual economic viability will be.
For biogas plants on cattle farms, the minimum threshold for an economically viable project is 1,000–1,500 head of cattle or the equivalent in terms of biogas yield.
The feasibility study is carried out by an EPC contractor or a specialist consultancy firm. Duration: 1–2 months.
Design involves developing a detailed technical solution tailored to a specific site. The project duration is 2–4 months. A high-quality design helps to prevent most errors during construction and reduces the risk of work stoppages.
In some cases, it may be necessary to undergo an Environmental Impact Assessment (EIA) in order to obtain planning permission.
The design phase concludes with the review of the design documentation — without this, a building permit cannot be obtained. The implementation period is an additional 1–2 months.
This is the longest and most complex stage, taking between 6 and 9 months under standard conditions. Preparing documents in parallel shortens the timeframe, but requires experience and knowledge of the regulatory framework.
An Environmental Impact Assessment (EIA) is mandatory for facilities processing more than 100 tonnes of animal-derived organic matter per day. The procedure typically takes 6–9 months on average, but may take up to 12 months, taking into account public consultations.
A permit for the discharge of pollutants (IDD) is obtained separately from the EIA procedure.
Temporary simplifications were introduced by CMU Resolutions No. 1320 and No. 547, as well as NEURC Resolutions No. 875 and No. 832 of 2024. Now is the ideal time to launch the BGS construction project.
It is important to note that a return to standard procedures is expected once martial law has been lifted.
The cost of equipment accounts for 40–50% of the total project budget. Lead time from order to delivery: 7–12 months for European equipment. This stage can be combined with the process of obtaining permits to save time.
The quality of feedstock preparation for a biogas plant directly determines biogas yield. Poorly prepared feedstock reduces reactor productivity by 15–20%. Equipment required:
Pro-Energy uses equipment from a trusted European manufacturer — HoSt Bioenergy Systems. This ensures reliability and access to after-sales support.
Construction and installation work takes 6–10 months and is the most resource-intensive phase. 25–35% of the total budget is allocated to the construction of fermenters and the installation of equipment.
Commissioning of the BGS — 1–2 months of work by the equipment supplier’s engineers and the plant’s own staff. The quality of this stage determines whether the plant will reach design capacity on schedule.
A biogas plant is a dynamic biotechnological facility. Staff must understand the biochemistry of the methane fermentation process. Without this understanding, operators react to deviations too late, resulting in a loss of productivity.
Commissioning is the final step before the commercial launch. Duration: 1–2 months. At this stage, the plant gradually reaches its design capacity rather than starting up at 100% immediately.
Examples of Pro-Energy projects confirm that, provided the plant is commissioned correctly, it achieves 95%+ of its design capacity within the first month of stable operation.

The estimated construction cost of a biogas plant is from €2.5 million per 1 MW of installed capacity (according to data from the International Renewable Energy Agency (IRENA) and the European Biogas Association “Biogas and Biomethane in Europe“ report). For a 2–3 MW plant (a typical size for an agricultural holding), the total CAPEX is €5–9 million. Below is a breakdown of costs by item.
| Cost item | % of the budget | Comment |
| Equipment (reactors, CHP, gas scrubbing) | 40–50% | The largest item of expenditure |
| Construction and installation works | 25–35% | Earthworks, foundations, installation |
| Design and Feasibility Study | 3–5% | Stage P, RP, expert assessment |
| Permit documentation | 2–4% | Vehicle registration certificate, technical inspection certificate, state duty |
| Commissioning work | 2–3% | Commissioning, staff training |
| Unforeseen expenses | 5–10% | Mandatory budget reserve |
| IN TOTAL (approximately) | 100% | From €2.5 million per 1 MW of installed capacity |
Never plan a budget without a contingency fund. 5–10% for unforeseen expenses is not an over-caution, but an industry standard. Projects without a contingency fund face construction delays or are forced to compromise on quality.
Most of the problems encountered during the construction of a biogas plant are the result of avoidable mistakes. Here are the seven most common ones, each of which has cost real-world projects time and money.
Choosing the right EPC contractor — a company with a track record of completed projects, rather than just impressive presentations — helps to avoid most of these mistakes.
The construction of a biogas plant is an 18–24-month project comprising seven consecutive stages. The longest stage involves obtaining planning permission, whilst the most expensive involves the equipment and installation. The most critical phase for the project is the start: errors in the feasibility study and design can prove most costly.
Three key factors for success: high-quality preparation of the raw material base, an experienced EPC contractor, and a realistic budget with a 15–20% contingency. Now is the best time to launch: simplified permitting procedures, international support, and growing demand for biomethane in the EU.
Please contact the Pro-Energy team for advice. We offer turnkey construction of biogas plants — from feasibility studies and design to commissioning and maintenance. We will calculate the payback period for your business and assist you with all the necessary permits and approvals.
How long does it take to build a biogas plant?
From concept to launch — 18–24 months. The longest stage is obtaining permits (6–9 months, but this can take up to 12 months); the shortest is commissioning (1–2 months). Carrying out some steps in parallel makes it possible to reduce the timeframe to 14–18 months.
What are the main permits required for the construction of a BGS?
For a standard project, the following are required: urban planning conditions and restrictions, land title documents, an environmental impact assessment for facilities handling more than 100 tonnes of manure per day, technical specifications for connection to utilities, a project assessment, and a building permit. During the period of martial law, most of these procedures have been simplified.
How much does it cost to build a biogas plant?
Approximately €2.5–3 million per 1 MW of installed capacity. Breakdown: equipment — 40–50%, construction — 25–35%, design and permits — 5–9%, commissioning — 2–3%, contingency — 5–10%. The final figure depends on the type of feedstock, technology, and grid connection conditions.
What is the minimum capacity that is economically viable?
For livestock farms — from 1,000 kW (1,000–1,500 head of cattle + crop waste). The optimal range for a quick return on investment is 2–3 MW. Smaller projects are possible if several farms collaborate or if the raw materials are available free of charge.
References to the sources used in writing this article:
Send us a request, and we’ll personally provide the answers during a consultation.
Thank you for your request! The manager will contact you shortly to answer all your questions.
In the meantime, check out our implemented projects.
Periodically, you will receive letters from us with all the latest news from the field of bioenergy.
So that the letters do not end up in spam, please add info@pro-energy.com.ua to the list of contacts in the mail.
We will be in touch!