0%

A power cut won’t halt production: how the CHP operates in island mode

author photo

Oleh Yovzhenko — 04.08.2026

Content

The power cuts of 2022–2025 have shown that, without a backup power supply, business comes to a standstill along with the grid. A few minutes of downtime on the production floor can cost tens of thousands of hryvnias. The shutdown of refrigeration equipment, breaches in temperature control, and production line stoppages — all of these result in direct financial losses. That is precisely why an increasing number of Ukrainian businesses are moving away from backup power supplies towards on-site power generation.

Cogeneration during a blackout is a fully-fledged source of autonomous power supply. If the cogeneration unit is already running, island mode allows the facility to continue operating automatically after the external grid fails. If, however, the unit has been shut down, the Black Start function is required to restart it at a facility that has lost all power.

This article will be useful to manufacturing companies, the food industry, logistics operators and data centres — anyone for whom a power cut results in direct financial losses. 

What is the CHP island mode?

Island mode refers to the autonomous operation of a cogeneration plant without any connection to the external electricity grid. The CHP plant becomes the sole source of electricity for the facility, and the enterprise effectively operates as a separate local power system: it independently generates, consumes and balances the load, without the involvement of a grid operator or plant operator.

That is why a company’s backup power supply is now regarded as a strategic element in ensuring business continuity. A cogeneration plant supplies electricity to critical systems and core production facilities even during large-scale power cuts. 

When is stand-alone mode activated?

The system switches to stand-alone mode in several typical situations:

  • a complete loss of external network connectivity — a blackout;
  • an accident on a power line;
  • scheduled power cuts by the network operator;
  • a critical deterioration in the quality of electricity — fluctuations in voltage or frequency beyond acceptable limits.

Island mode is activated provided that the combined heat and power plant is already in operation or ready for an automatic switchover. If the CHP plant was not in operation at the time of the blackout, the Black Start function is required to start it up.

The difference compared to operating in parallel with the mains supply

In parallel mode, the CHP unit and the grid operate simultaneously: the unit covers the base load, whilst the grid supports peak demand. In island mode, the grid is physically disconnected, and the CHP unit alone handles the entire load. The switch between these modes occurs automatically, without manual intervention.

In effect, the off-grid CHP takes on the full role of a local power station: it maintains frequency and voltage and ensures a stable power supply to all priority consumers. 

How does the switch to island mode take place?

Automated script

In the event of a power cut, the system responds according to a clear sequence of actions.

  • Step 1. Fault detection (0–1 second). The monitoring system detects a loss of mains voltage and the backfeed protection is triggered.
  • Step 2. Disconnection from the mains (1–3 seconds). The circuit breaker disconnects the unit from the mains, isolating the CHP from the external circuit.
  • Step 3. Stabilisation of the CHP (3–10 seconds). The unit switches to autonomous frequency and voltage control, and load balancing takes place.
  • Step 4. Power supply to critical loads (10–30 seconds). Once the emergency power unit has stabilised, the system gradually reconnects the loads. First the critical systems, then the main production facilities.

The total transition time is 10–30 seconds.

What happens to the equipment during the transition?

A brief power interruption of 10–30 seconds may occur. It is during this period that critical equipment — servers, automation systems and security systems — is supported by the UPS. Once the switchover is complete, the facility receives a stable power supply from the power generation unit without any further fluctuations.

Island mode and Black Start — what’s the difference?

Island mode and Black Start are different operating modes for a combined heat and power plant, although they are often confused.

Island mode is used when the UPS is already operating in parallel with the external mains supply. If the mains supply fails, the automatic system disconnects the facility from the mains, and the unit continues to power the facility autonomously. It is this scenario that ensures uninterrupted operation during a power cut.

Black Start is the ability to start a cogeneration unit at a facility that is completely without power, when neither the grid nor the cogeneration unit itself is operational. This requires a separate power supply system for the unit’s own needs (batteries or an auxiliary power source), which enables the engine and control systems to be started.

Not all cogeneration units come with a Black Start function as standard. If a business requires a fully autonomous start-up following a total power cut, this requirement should be taken into account as early as the design and equipment selection stage.

How CHP is switching to island mode

Technical requirements for stand-alone operation

For the island mode to function correctly, the installation and associated equipment must meet a number of technical requirements.

CHP Equipment

  • automatic frequency and voltage control system;
  • engine speed controller;
  • automatic voltage regulator (AVR);
  • synchronisation system — to ensure a correct return to parallel operation.

Switching equipment

  • motor-operated circuit breaker;
  • AVR system (automatic reserve injection);
  • prevention of parallel operation in island mode.

Control system

  • controller for stand-alone operation;
  • load prioritisation system;
  • monitoring of parameters — frequency, voltage, power;
  • overload and short-circuit protection;
  • an automatic load control system for the consumers supplied by the plant.

Additional equipment

  • UPS for mission-critical systems — servers, automation systems;
  • a soft-start system for large motors;
  • capacitor banks for reactive power compensation.

Features of operating in standalone mode

Frequency control

Under normal conditions, the frequency of the grid is maintained by the power system. In island mode, this function is performed solely by the CHP: the motor speed controller maintains the standard 50 Hz on its own.

Voltage control

The AVR maintains a stable voltage and compensates for fluctuations in the event of a change in load, for example, when starting up high-power equipment.

Power limitation

The generator set is physically incapable of exceeding its rated power. If the load increases excessively, the priority system automatically shuts down non-critical loads, whilst the overload protection prevents the unit from being damaged.

Starting currents

During start-up, electric motors draw 5–7 times their rated current. For this reason, equipment is started up in stages, and soft-start systems are used for large motors — otherwise, the power distribution board may not be able to withstand the peak load.

What can power CHP in island mode?

Critical systems (priority 1)

Emergency lighting, security and fire-extinguishing systems, servers and communications, and ventilation where it is critical.

Core production (priority 2)

Production lines, refrigeration equipment, compressors, pumps.

Support systems (priority 3)

Office equipment, non-essential lighting, air conditioning for comfort.

What might be disabled

Electric heating — if the property is already supplied with heat from the central heating system, decorative lighting, and non-critical equipment. This is not a compromise on functionality, but a way of conserving the system’s capacity for the main heating supply.

Examples of the use of island mode

Logistics complex, Poltava Region. The team commissioned two 2G cogeneration units with a combined capacity of 675 kW of electrical power and 701 kW of thermal power. The equipment was commissioned in October 2025 following a 9-month implementation period, in partnership with 2G Energy AG (Germany). The Agenitor 406 (275 kW) and Agenitor 408 (400 kW) units operate in three modes: grid-connected, stand-alone “island” mode, and start-up during a total blackout. The complex’s overall efficiency is 85–87 per cent. The cascaded operation of the two units has made it possible to flexibly adapt generation to seasonal loads: in winter, the 400 kW unit carries the main load, whilst during periods of lower consumption, the 275 kW unit takes over. The project was installed without disrupting logistics operations; some of the work was carried out at night, with the facility temporarily switched to backup power. The result is 100% coverage of the facility’s electricity and heating needs, and a foundation for a future microgrid comprising a solar power plant and energy storage systems. 

You can find out more about similar completed projects in the company’s portfolio.

Shopping centre, Lviv. The client had already purchased an AVUS 1000 Plus (2G) combined heat and power unit with an electrical output of 1,000 kW and a thermal output of up to 1,045 kW. They then requested a rapid commissioning of the equipment without interrupting the facility’s operations. Installation and commissioning were completed within one month, in accordance with the manufacturer’s specifications. The unit runs on natural gas, with an overall efficiency of 89.4 per cent. Part of the load is additionally covered by solar power generation — a hybrid model combining cogeneration and a solar power plant. The project demonstrates how quickly off-grid operation can be integrated into the existing infrastructure of a commercial facility without posing any risks to operational activities.

These projects confirm that energy self-sufficiency in production is now a prerequisite for the stable operation of a business in the context of an unstable power grid. 

How long can the CHP operate in stand-alone mode?

Limiting factors

The duration of autonomous operation depends on the fuel reserve, the engine’s continuous running life, the engine oil reserve and the maintenance schedule.

Typical figures

The duration of autonomous operation between refuelling stops is determined by the service specifications for the specific model, operating conditions and fuel quality. Scheduled maintenance intervals must be specified in accordance with the manufacturer’s documentation for the selected unit. When connected to the gas network, operating time is virtually unlimited; when operating on biogas, it depends on the availability of feedstock. 

The financial cost of this level of energy self-sufficiency can be estimated in the article on the cost of a combined heat and power plant in Ukraine.

Returning to parallel mode

How it works

Once the external mains supply is restored, the system detects this automatically, checks the quality of the mains supply, synchronises the generator set with the mains in terms of frequency, voltage and phase, and only then reconnects the unit to the mains.

Return time

Automatic restoration takes 1–5 minutes once the network is back online — without the need for staff intervention.

Comparison: CHP vs diesel generator for backup power

Parameter CHP Diesel generator
Battery life Unlimited (if it’s gas) Limited by fuel supply
The cost of electricity Low High
Heat recovery Yes Usually not
Energy savings in normal mode Yes (parallel operation) No (reserve only)
Environmental friendliness Higher Lower
Noise Lower Higher

The key difference is that a diesel generator operates solely as a backup and remains idle most of the time, whereas a diesel generator set saves on energy costs on a daily basis and, in the event of a power cut, simply switches to stand-alone mode without incurring any additional costs for maintaining a separate backup source.

Common mistakes when organising an island mode

A properly designed island mode system provides comprehensive protection against blackouts, covering not only the combined heat and power plant but also automation systems, load prioritisation, UPS systems and regular equipment testing. At the same time, the following mistakes are often made during the design and operation of a facility: 

  • insufficient capacity of the gas-fired unit, which does not cover the critical load;
  • the lack of a priority system — this leads to overload when equipment is started up simultaneously;
  • there is no UPS for critical systems, so data is lost during the 10–30 seconds that the switchover takes;
  • start-up currents have not been taken into account — the CHP “trips” when powerful engines are started;
  • lack of testing — a system that has never been tested is highly unlikely to work in a real-life situation;
  • there is no contingency plan for staff — panic during a blackout instead of a clear procedure.

These and other practical challenges associated with implementation are discussed in more detail in the article on the challenges facing cogeneration in Ukraine.

Checklist for preparing for island mode

This model is not only relevant to large factories — off-grid operation is increasingly being adopted by smaller facilities as well, as described in the article on cogeneration for small and medium-sized businesses.

The main thing to remember

The cogeneration unit’s island mode ensures the facility can continue to operate uninterrupted during power cuts. If the cogeneration unit is already running, the switch to island mode takes place automatically within 10–30 seconds. However, if a shut-down CHP unit needs to be restarted following a complete power cut at the site, the design must include a Black Start function. Unlike a diesel generator, a CHP unit not only serves as a backup power source but also enables energy savings during day-to-day operation. The key to reliable operation lies in correctly calculated capacity, a properly configured load prioritisation system and regular testing. For insights into the prospects for the development of such solutions in the coming years, read our article on cogeneration in Ukraine in 2026.

Would you like us to assess which off-grid configuration would be best suited to your specific site? The Pro-Energy team will carry out an energy audit and propose solutions tailored to your actual load profile — from power calculations to commissioning and staff training.

Frequently Asked Questions

Island mode refers to the autonomous operation of a combined heat and power (CHP) plant without connection to the external electricity grid. The CHP plant becomes the main controlled source of the local power system or operates as part of a microgrid alongside other generation sources.

The automatic switchover takes 10–30 seconds, provided that the GSU was already operating in parallel with the external grid. If the unit was shut down, the Black Start function is required to restart it following a complete power cut.

When connected to the gas mains, the engine has an unlimited service life. When running on biogas, this depends on the supply of raw materials. A typical continuous operating cycle for the engine is up to 4,000 hours (half a year), after which scheduled maintenance is required.

The CHP unit is energy-efficient even in normal operation (running in parallel with the grid), has an unlimited operating time when connected to the gas supply, recovers heat, has lower electricity costs and is more environmentally friendly.

Technical requirements: automatic transfer switch (ATS), island mode controller, frequency and voltage regulator, load priority system. Recommended: UPS for critical systems, soft start for large motors.

Got questions for the Pro-Energy team?

Send us a request, and we’ll personally provide the answers during a consultation.





    Related articles

    What CHP capacity does your business require? A practical calculation method
    What CHP capacity does your business require? A practical calculation method
    The most common question asked by business owners before implementing cogeneration is: “Which cogeneration unit should I install?”. In ...
    • Cogeneration
    Cogeneration for hotels and shopping centres: case studies and calculations
    Cogeneration for hotels and shopping centres: case studies and calculations
    Hotels and shopping centres are facilities with consistently high energy consumption, where electricity, heating and cooling are required every day...
    • Cogeneration